Hi PP gurus,

can anyone please tell me how to enter downtime for the resource in PPPI? I am using R/3 6.0 and the transaction DTR0 does not work. the initial screen for DTR0 comes but it does not process further once the plant and resource are entered but displays an error message "An error occurred while displaying the downtime." Please help.

Thanks and regards

Abhik Datta

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 06:10 AM

    Hi,

    Downtime analysis is available only with APO.

    This has been already answered in the following thread

    Downtime analysis

    Message was edited by:

    Kannan S

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 07:47 AM

    Hi Abhik

    For entering the down time for a Resorce, You can use the t.code kb21

    1.) Enter cost center

    2.) Prodn order number,

    3.) In the field of quantity.you can enter no.of hrs and select the Unit of Measurement as hrs

    This may solve u'r problem

    Reward points,if usefull

    Regards

    Palaniappan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.