on 11-23-2007 5:35 AM
Hi,
Please give solution for the below mentioned scenario.
There are 2 materials X,Y which are dependent on each other in scheduling for example shaft(X) is to machined based on the bore(Y) size.
Production order is created for both the materials X and Y.
Operation sequence for the bore(Y) is as follows:
10 Cutting
20 Turing
30 Boring
40 Milling
50 Drilling
Operation sequence for the Shaft(X) is as follows:
10 Cutting
20 Turning
30 drilling
40 milling
My requirement is in the production order, scheduling should be done for operation 20(Turning) of shaft(X) after finish date of Operation 30(Boring) of bore(Y) i.e If Operation 20(Turning) of shaft(X) is scheduled on 12-11-2007, then Operation 30(boring) of bore(Y) is finished before 12-11.2007. Is there any possibility to link the operation wise scheduling of two production orders.
Note:
1.Both the materials have different BOM.
2.Both have different work center.
3.Both materials are assembled in later stages
Hi,
You can try this by manual dispatch of the material (X) to the concerned date by knowing the date of the 30 Operation of material(Y) using Capacity Levelling.
Try this process...
- Thaila Shree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Afzal,
There is no standard option available for your requirement. You need to develop a custom program for this.
The only option what I can think of is using Collective Orders Scenario. Pls explore this option, before getting into program development.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.