Integration of HR with Production

Dear All,

I am a PP person and looking for ntegration of HR at work center.I am trying to link a person in work center using HRMS tab,but I don't find any values for Person.

Kindly let me know the steps to be followed to create persons and other relevant data.Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 03:26 PM

    Hi,

    A person is possible linked to a position in organizational managment in HR and work centers can be managed at that level. Also if a person is linked to a work order for costing, they can be linked to a work center at this level.

    thanks.

    Jamie

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 24, 2007 at 10:53 AM

    If your are using transaction CR02, then there the Person Responsible is coming through your customising activity. Check IMG Activity Production>Work Centre>Determine Person Responsible.

    If you are in some other transaction please give details.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.