Skip to Content
0

Can I reverse a production order in a closed period after both confirmations in CO13.

Oct 13, 2017 at 08:47 AM

44

avatar image
Former Member

Hello,

We had filled out a production order in August.

After both confirmations for some reason the order was not able to be fulfilled.

So now we are trying to reverse the order without having to open up the previous period.

We tried CO13 but were unable to get it to work for a closed peiod.

Thanks for the help!

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Oleg K Oct 15, 2017 at 11:19 PM
0

just reverse it in the current (open) period.

put today's date in a Posting date field

Share
10 |10000 characters needed characters left characters exceeded