Production Order settlement

Former Member
0 Kudos

Hi,

I am trying to settle a pord order Tcode KO88, when i tried doing so, i encounterd an error, stating "complete the PA transfer structure Z1", how to proceed about it??

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

go to KEI1 and complete the configuration for Z1 structure....

You have to assign source to values....

If helpful asign points..

Cheers

PK

Former Member
0 Kudos

Hello Ranganathan,

You might have entered PA transfer structure in your settlement profile. PA Transfer structure is relating to transfer of Variances to COPA. You goto Settlement profile and see wether you have given PA Transfer structure, if you need it, then you define the details of transfer structure with mapping of cost elements or variances to value fields in COPA, if not required, remove from settlement profile.

Hope this helps you.

Please let me know if you require any further information.

Thank you,

Regards,

Santosh