Hi Experts,
How to set the batch job for sap standard program? my requirement is 1." every sunday night
all the items should be processed to tables.
2. On 3rd business day after period end where the closed period must me processed again..
Could you please tell me what are the steps involved while creating the background job scheduling for this requirement...
Thanks in advance.
rewards for helpful points.
Regards,
DR.
11-22-2007 7:16 AM
Hi Rekha
In SM36 -> For point 1 -> Put the start date as a date which falls on Sunday and in the <b>period values</b> choose "<b>Weekly</b>" This should hopefully schedule it every week.
Point 2 -> please explore how you can use the Factory Calendar in SM36
Regards
Arun