COPC...standard cost estimate

Hi all,

When I generate the standard cost estimate in ck11n, it will come out some figures...but can anyone tell me where the system pull the figure out?

thanks,

Lucas

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2007 at 06:39 AM

    Hi Lucas,

    it will pull data from various master records like BOM, Routing, Material masters etc.

    Example: you have 2 Rawmaterials and one finshed product.

    so when you do costing for Finished cost

    it will go the the BOM and check the BOM components ex:- 2 Raw materials

    it will select the price from material master records of both the masters records

    Overheads costs will pick from the costing sheet

    Activity price calucltion from KP06

    Routing it will calculate the actual activities requeired for this operation.

    Costing variant will be the key role in costing, it contain Valuation variant etc...

    Lot of configureation will depends on master data configuration

    Best Regards

    Ashish Jain

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.