i have finished materials A, B ,C, D

with requirement qty 200, 300, 4000, 500 for thesematerial respectively for mnth of DEC 2007.

i have to carry out MRP for all these 4 items for one mnth,

what are the different way to carry out MRP for this?

Regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2007 at 05:30 AM

    HI,

    You can run MRP with following ways-

    1- by putting requirement for all four materials in MD61

    2- by planning through regular rough cut- planning and then transfer data to demand management.

    3- for above run your planning strategy will be 10 i.e. MTS

    4- FOR MTO scenario you will require sales order then with ref. of that sales order you can run MRP.

    don't forget to reward the points to this answer if it is helpful to you,

    Regards,

    Amit.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2007 at 05:42 AM

    Hi Ajay..,

    Maintain the planning horizone as one month.

    regards.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 22, 2007 at 05:46 AM

    Hi,

    You can use MD02 transaction to run mrp for these materials individually.

    If you want to run mrp for plant use MD01 or MDBT(background run).

    Regards,

    Senthilkumar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 22, 2007 at 05:50 AM

    Ajay,

    You need to first maintain a Planning horizon of 30days(or suitable as required) in transaction "OMDX" for the MRP group which is assigned to the Materials A,B,C and D in the MRP1 view.

    Now you have to run MD02 transaction for every material with Processing key as <b>NETPL</b>.

    Or else,

    You need to activate the user exit for MRP1 to select Materials based on a condition in your case to pick up A,B,C and D material. And run MD01 with processing key <b>NETPL</b>.

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.