Hi all,

I am trying to use VPRS to show the std.price. I have done the below,

1.In item cat TAN I have set the "determine cost"

2.In item cat TAN I have included the X indicator for Pricing.

3.In pricing procedure VPRS is set statistical with req 004.

But still I hit problem as it is not copying the cost from Material Master.

"Error in quantity/value determination" with Message 217.

Diagnosis

This condition has not been determined using condition records. The amount or value should be determined from another data source. For cost (condition category 'G') it is read using conditions from the material valuation segment, for a cash discount condition it is read using conditions from the terms of payment table.

In this transaction an error occurs - the material valuation segment or the terms of payment table could not be read or a currency translation has failed.

System Response

The condition has been provided with the deactivated indicator 'X'.

Pls advise where should I look for this deactivated indicator 'X'

The condition has been provided with the deactivated indicator 'X'.

Thanks in advance!

Rgds,

pri

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

9 Answers

  • avatar image
    Former Member
    Nov 22, 2007 at 05:58 AM

    Hi,

    Can you just have look in is there any billing plans in that order,also check have you entered plant in the order.Because the logid of the routine 4 progrm is above.If any billing plans are there VPRS will not work. also plant should be eneterd.

    Regards,

    Chandra

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Chandra, just forgot to say that I have not even saved the sales order. I just created & went to the Condition tab & looked into Analysis..

  • Nov 22, 2007 at 03:47 AM

    Dear Anne

    Go to <b>OMS2</b>, select your material type for which it is giving the error. Click "Qty/updation" tab on left side. Here mark the two boxes for the combination of plant and material type in the field "Qty updating" and "Value upd".

    Thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Lakshmipathy,

      Yes, it is ticked under HALB & the plant. It is appearing for all materials.

      Any idea? Or anything is missing...Pls advise.

      Regards,

      Pri

  • avatar image
    Former Member
    Nov 22, 2007 at 04:01 AM

    Hi,

    The link below will help you.

    http://sap-img.com/sd021.htm

    Reward points if it helps.

    Regards

    Karan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Karan,

      My company uses PR00 & also VPRS.

      My problem is not resolved yet....please do help if anyone has idea.

      Regards,

      Pri

  • avatar image
    Former Member
    Nov 22, 2007 at 04:15 AM

    Hi Anne,

    Have you Maintained the Standard Price in the Material Master in Accounting Tab..

    and in the pricing Have u maintained B in the sub total for VPRS Condition and Stastical.

    Maintain Codition Category G in the Condition Category of the VPRS Condition

    Condition Class B

    Calculation Type C

    Maintain above things

    Hope This Will Solve u r Issue..

    Reward If Helpfull.

    Regards..

    Praveen Kumar.D

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 22, 2007 at 04:34 AM

    Hi,

    goto <b>T.Code MR21.</b>.Here maintain the Company code and Plant. and also maintain the material and the new price.

    regards,

    vas.v.s.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 22, 2007 at 04:39 AM

    Hi Anne,

    Are you using a Standard price or a moving average price?

    The condition has been provided with the deactivated indicator 'X', is a system response. You need not look out for that. You are already getting VPRS as deactivated in the sales order.

    The issue could be accessing the correct price in the valuation segment. Check which cost are you using , Standard price or Moving average price?

    Next, there is a control in the material master on the tab page 'Accounting 1' in the segment of current valuation, field control V or S.

    Check if this helps.

    Regards,

    PATHIK

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi all,

      I found the probelm. Just to update to you.

      mbew-zkdat is BLANK, so VPRS is determined as 0, and error 217 displayed.

      SAPnote 117714 for more help.

  • avatar image
    Former Member
    Nov 23, 2007 at 04:33 AM

    hi

    i think ur not maintianed data of plant, once in sales order the plant is derermeined the cost from the material master is picked by the order.

    regards,

    kris

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Krishna,

      I did maintain the plant in my Sales order. Still....I don't get the vprs cost..

      I have setup another condition type just for my testing of PR00, I named it differently. Will that affect this cost ?

      THanks,

      Pri

  • avatar image
    Former Member
    Nov 23, 2007 at 12:20 PM

    Hi,

    First check in pricing procedure and kept it as statistical condition and keep B in sub total column which is meaning of BCarry over value to KOMP-WAVWR (cost)'

    now come to condition record of VPRS keep this data

    condition class as prices

    calculation type:quantity

    cond category:cost

    In manual entry column:D

    ACTIVATE AS ITEM CONDITION.

    also check the MMR costing:2 view of moving and standard prices and keep price control accordingly.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 23, 2007 at 01:53 PM

    Hi Pri,

    Please go to Item Category and check the box Determine Costs in the business data column that will bring the VPRS and help in determining the std price, That should solve your problem.

    good luck mate

    krishna.Srirangavaram

    Add comment