SAP TM Planning TU with Schedule

Oct 14, 2016 at 05:38 AM

69

avatar image
Former Member

Hello Guru's

We are working on TM 9.1 with Trailer units, understand trailer units will not work with schedule.

What we are looking at is, we have train schedules, based on the train schedules we need trailers to be planned their main leg of transport apart from "pre" and "on" carriage legs based on active no-load resources.

Is this possible in TM 9.3/9.4?

Regards,

Badami

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member Oct 18, 2016 at 04:39 PM
0

Hello All,

To the benefit of the community I am updating the SAP response.

VSR optimizer will not support planning TU's planning with Schedule and the same is also not possible in new releases.

But in TM 9.4 can expect a new feature Load-Consolidation, which would be the main focus point for TU planning.

Regards,

Badami