Skip to Content
avatar image
Former Member

SAP TM Planning TU with Schedule

Hello Guru's

We are working on TM 9.1 with Trailer units, understand trailer units will not work with schedule.

What we are looking at is, we have train schedules, based on the train schedules we need trailers to be planned their main leg of transport apart from "pre" and "on" carriage legs based on active no-load resources.

Is this possible in TM 9.3/9.4?

Regards,

Badami

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 18, 2016 at 04:39 PM

    Hello All,

    To the benefit of the community I am updating the SAP response.

    VSR optimizer will not support planning TU's planning with Schedule and the same is also not possible in new releases.

    But in TM 9.4 can expect a new feature Load-Consolidation, which would be the main focus point for TU planning.

    Regards,

    Badami

    Add comment
    10|10000 characters needed characters exceeded