SAP TM Planning TU with Schedule

Former Member
0 Kudos

Hello Guru's

We are working on TM 9.1 with Trailer units, understand trailer units will not work with schedule.

What we are looking at is, we have train schedules, based on the train schedules we need trailers to be planned their main leg of transport apart from "pre" and "on" carriage legs based on active no-load resources.

Is this possible in TM 9.3/9.4?

Regards,

Badami

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello All,

To the benefit of the community I am updating the SAP response.

VSR optimizer will not support planning TU's planning with Schedule and the same is also not possible in new releases.

But in TM 9.4 can expect a new feature Load-Consolidation, which would be the main focus point for TU planning.

Regards,

Badami