Dear PS gurus,

In CN41 Project Info System, selected ps profile 00000002, and given a project definition, below layout is under use :

Project Object : Project Description

Project Object : Project codes ( project definition, WBS, Network)

Start (B) : date is displayed

Finish (B) : date is dispalyed

Actual duration : nothing displayed

Start ( A) : date is displayed

Finish (A) : date is displayed

Duration : nothing displayed

can u pl let us know why actual duration & duration - days are displayed in both.

pl help how the duration is displayed at cn41.

pl help

regards

Srihari

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2007 at 05:33 AM

    Hi Srihari,

    Kly recall teletalk we had.

    I repeat what I explained earlier:

    Confirmation of assigned activities will update the following date fields in the WBS element( provided "no date update" is not selected in the confirmation transaction):

    1) Tentative actual start date

    2) Tentative actual finish date

    For tansferring these dates as actual dates, you can go ahead as below:

    Logistics->Project System->Dates->Actual dates->Edit ->Reconcile dates- Determine actual dates.

    Instead of the menu path, you can execute the transaction code: CJ25

    Input the project ID or WBS, select activity radio button and execute. This will open-up the entire structure. Select the WBSE for which you want to transfer dates from tentative to actual. Then edit->reconcile dates->determine actual dates

    With this tentative dates will be transferred as actual dates and actual duration also will get updated.

    Hope thie solves your problem.

    If so, kindly acknowledge the same.

    Muraleedharan.R

    091 9880028904

    Add a comment
    10|10000 characters needed characters exceeded

    • Dear Muraleedharan,

      thanx so much for your solution,

      it is perfectly working & getting the dates & duration upto WBS element level. I can see at cn41.

      Now, request, pl advise, how i can get the Duration (A) at Project Definition level in CN41 level, pl help.

      Regards

      Srihari

  • author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2007 at 02:57 AM

    Hi Srihari,

    Please check in the project builder against corresponding WBS elements (under date tab) whether duration is calculated. If duration is calculated in the project builder, there is no reason why it is not captured in the report.

    Muraleedharan.R

    091 9880028904

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.