Hi SAP Gurus,

1>If we will take account assignment, Purchase requisition valuation price, and Material group as catechistic for release procedure of PR. Then my question is whether the release strategy tab will populate in the PR only if the all the value as per the release strategy will meet?

2>My 2nd doubt is can we take the price as a releasing factor for PR. Could you please explain me this part ( on the PR Valuation price). Whether it will take the valuation price or the total value of the PR?

Thanks

Sha

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 11:59 AM

    Two types of release procedures are there

    1. With classification (Header level release i.e overall release can be possible)

    2. Without classification (Item level release)

    Release procedure without classification can be configured only for purchase requisition.

    For PR at any given time only one release procedure can be active

    Release procedure for PR without Classifications:

    Structure:

    1.Release Codes: Release codes are the approved hierarchy or levels involved in releasing of a document. (Max: 8 approve levels Ex: CEO, GM, Mgr etc)

    2.Release Indicators: Used to determine the status of purchase document. Ex: Blocked, Relesed for RFQ/Q or for PO.

    3.Release indicator assignment: In this activity we will define the status of purchasing document at each approval level.

    Release Prerequsites:

    1. Sequence of release

    2. Release strategy (It is the combination of release pre-requisites and release indicator)

    Determination of release strategy:

    Hence we will configure based on what criteria, or based on what variables the release strategy is going to be effected. Ex: Item Value, Plant, Material group etc.

    Navigation: MM-> Purchasing->PR->release procedure-> Setup procedure without classification

    1. Select release codes

    2. Release indicator

    3. Assign release indicators

    4. Release points - prerequisites

    5. Determination of release strategy

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.