This is w.r.t the invoice verification MIRO when Qty lay in QM Lot.

Scenario 1: The MIGO is done and 100 Qty is Moved to QM lot,During this

condition the system should block the MIRO transaction w.r.t Material

document.(MIRO- should not be allowed (saved) untill the qty is cleared

form QM lot).

Scenario 2 : The MIGO is done and 100 Qty Moved to QM lot. During QM

check,the 90 qty is accepted and 10 qty is rejected (blocked stock).

The client requirement is MIRO should be allowed for only 90 qty not

for the 10 qty which is rejected.(system should propose only for 90qty

should not accept more than 90.)

Kindly guide how to proceed on this issue.

Is there any work around for this issue.

The above mention issue , we faced with the earlier client also. I would why SAP doesn`t covered it.

Biswajit

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 10:41 AM

    Dear Biswajit,

    your question is very correct, but as the stock in QI is also a valuated stock of your company and not the supplier.Taking this logic in consideration the system allows to do MIRO even if the stock is in QM.

    Hope solved your querry.

    Njoy

    Ashish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 10:52 AM

    in material master of that material in QM view

    put 0007 in QM control KEY

    hope this will solve the issue

    regarsds

    umakant

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hello Biswajit

      please use user exit and z program

      Z prog for user exit - Invoice verification posting not allowed if QA not

      only Zprogram will help u in Invoice verification posting not allowed if inspection lot not cleared in QA

      Reward if issue solved

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.