Po-Release Problem

Dear All,

When I create Po through ME21N , system adopt the Release strategy.But if I tried to Release through ME29N system showes the Message of "PO CAn not Release" and I did not get the Release Icon in ME29N.Please Suggest if any config Change req?

Thanks,

Manis,

UK

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 09:55 AM

    dear manis,

    Please check with the basi guy that does your user has authorisation for PO release or not.

    otherwise tell me what is ur criteria for release strategy ie document type, total PO amount, Purchase Org. etc.

    Please check and revert back.

    Njoy.

    Ashish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 10:03 AM

    Hi Mani,

    First check the PO release authorization for your ID

    If its in place run check release strategies option in S

    spro>mm>purchasing>po>rel stat>check relese stategy

    there should be all green indicators

    check red ones and clear the defects

    BR

    Diwakar

    reward if useful

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.