Dear All

For third scenario, From sales order our SD people triggering PR. In MM we have completed PO,MIRO.

Now the PO details updated in Sales order. In document flow icon we are getting what are the PO raised for that sales order.

Now my requirement is

Our SD people raising Invoice by actual amount of PO + 5% margin.Now they want basic price from PO should come automatically to sales order conditions tab. Or any other way is available to maintain selling price of the material.How to match this scenario.

Please guide me.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 10:28 AM

    Hi

    For third party scenario, the SD can raise the Bill to customer, only after the Vendor invoice is posted.....Based on Vendor's Invoice only they can create billing document to the customer.....with out IV, they cannot bill.

    If you very particular about PO price....Create condition record in VK11...for the necessary condition types....accordingly configure Pricing procedure in SD.....

    Reward if useful

    Regards

    S.Baskaran

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 10:18 AM

    Hi

    In the Third party process first the Sales order is created & in that you are giving the conditions.

    So using condition records you can maintain the sellling price for the material.

    using VK31

    If you want to display the material cost in Sales order condition tab , use Condition type VPRS or P101 in the SD pricing procedure.

    These two condition types pick the value of the material from the material master

    Reward points if useful

    Thanks & Regards

    Kishore

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.