Hi

After successful release of the process order, the system does not create a TR in background. It gives me the error "No WM relevant components exist (function not possible)'. The order components are WM relevant, have maintained control cycle at the plant/supply area level, PP interface is maintained at OMK0. Is there anything else I'm missing? Please help.

thanks

BE.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 21, 2007 at 06:18 AM

    Hi Brian,

    Have you maintained the setting in SPRO (CORY),That is, WM transport request to be created during the order release.If not activate this.

    Regards

    rajesh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 21, 2007 at 06:28 AM

    For the Production Schedule profiler in the plant under the Transport tab

    WM Request X Only creation of transfer requirements on release

    Use transaction OPKP to do the above.

    Add this production scheduler profiler in the Material master and also check the settings in the Order type.

    Hope this helps you.