Scheduling for labor capacity

Hi Guys,

While doing production order scheduling labor Work center is not getting schedule,it is showing warning message (No capacity category maintained in work center for scheduling).but i checked in the particular Work center the capacity category is maintain correctly .Because of this problem capacity requirement is not creating for the labor capacity.

please guide to solve this issue

thanks in advance

S.Murali

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 21, 2007 at 06:41 AM

    Hi

    If you observe the scheduling tab of work center , it has a provision to schedule one of the capacity category.

    If you have already made settings for machine work center , you can not schedule the labour capacity.

    As per SAP , only machine should be schduled , because machine is a costly resource yhan the labour.

    If you want you can do it only labour capacity.

    You can schdule only one capacity category.

    Hope it is clear.

    Regards

    YMREDDY

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      You have to make some specific settings in work center.

      1) you have to select cpacity category in capacity tab as 002 ( never mind even work center category can be machine also)

      2) in scheduling tab you have to selct capacity category as 002 .&

      3) you have to give correct formuals required for labour ie in capacity tab std formula is SAP007 & in SAP003 in scheduling tab in Processing formula field.

      4) If you have set up also you can give SAP005 in capacity & SAP001 in scheduling tab.

      5)If you have shift sequence , you have to configure properly

      6) In capcity header screen acive version filed should be filled appropriately.

      7) mIn the capcity header screen you have check the box " rlevent to finite scheduling,

      Pl,check & try.

      If it is solved pl awrd with full pints else pl. update.

      Regards

      YMREDDY

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.