Hello experts!

i have detected an issue at my system when i set the Automatic

Source Determination flag when i change a Purchase Requisition at

ME52N.

Here is the situation.

If we set this flag at the PR creation (ME51N), the source

determination is well done.

However, if the user forgets to set flag "Auto Source Determination" at

the PR creation, at ME52N when it is set, the Source is not

determinate automatically...

If you press button "Assign Source", it is brought to the PR correctly.

Is there any OSS Note that solves this mistake??

Thank you very much in advance.

Regards,

cecil

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2007 at 03:36 PM

    Hi Maria

    The header level "source determination" check box is intended for getting the appropriate source for <b>each</b> PR line items while <b>creation</b>.

    As you have created PR lines already without choosing this option, now by simple selection in ME52N will not assign source. You have to use source assignment at individual item level.

    warm regards

    sairam akundi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.