on 11-20-2007 12:23 PM
Hello Gurus!
Can anyone please help with the following problem:
Im trying to do the material cost estimate with quantity structure, but the system is throwing back the message " There is no exchange rate for exchange rate type P on 1.01.2008: CHF -> EUR".
This happens because I have a subcontratation in my routing in CHF, and in transaction OB08, and I dont had defined that rate (type P CHF EUR).
I need to know if there is any solution to the system assumes other Type of Exchange Rate (the last real exchange rate that I have introduced in my system, not the planned!)
Points will be assigned to the suitable answer.
Thanks in advance.
Mary Jane
In the valuation variant for the activity price tab you enter the version that is used for selecting the prices. In OKEQ, for the specific year & the version you maintain that 'P' is considered for forex conversion. You may either change the version, which can be configured to choose a preferred ex-rate type or change the ex-rate type for version 0.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.