We have a forecast loaded into SAP, is it possible to have different Requirement types as follows.

Make to Stock Orders consume forecat

Makt to Order Orders do NOT consume the forecast.

If this is possible where is this set-up/config'd

Kind regards,

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2007 at 05:32 PM

    Hi,

    Make strategy group 20. In that make combination of strategy 20 & 40.

    When make to order sales order , it wont consider forecast stock.

    When make to stock sales order, it will consume forecast stock (change requirement type in sales order).

    Create strategy group by using tcode OPPQ.

    Reward points if useful.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2007 at 01:34 PM

    Hi Guy,

    You can use Strategy 10 for this.

    Assign strategy group 10 in which the strategy 10 alone is maintained in the material master MRP3 view.

    Regards

    Krishna

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.