Transfer of apo planned order to r/3

Former Member
0 Kudos

Dear experts,

I have created the planned order from the interactive planning menu manualy in apo.That planned order i want to transfer to R/3.

How is it possible.

Regards,

Sunil Patil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Sunil,

you have to create a distribution defintion in customizing for the location and "inhouse production".

You should also create an integration model for that material in R/3 as well.

I assume the basic stuff such as logical systems, rfc-connections etc. are already done!?!

Hope this helps..

Niko