Dear experts,
I have created the planned order from the interactive planning menu manualy in apo.That planned order i want to transfer to R/3.
How is it possible.
Regards,
Sunil Patil
Dear Sunil,
you have to create a distribution defintion in customizing for the location and "inhouse production".
You should also create an integration model for that material in R/3 as well.
I assume the basic stuff such as logical systems, rfc-connections etc. are already done!?!
Hope this helps..
Niko