I have an issue related to MF60 Transaction.( Material Staging)

In my Case after creation of processes order i am trying material staging through MF60. But the process order no. (material that i want to do staging) is not reflecting in to MF60.

Please guide me.

Amit

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Nov 19, 2007 at 09:19 AM

    Amit,

    Check whether your order is Released (REL)?

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 19, 2007 at 09:22 AM

    Hi Amit,

    i hope u have created process order for Header Material and components of Header material needs to be staged.

    if there is no enough stock at production stoarge loaction (issue stoarge loc of components ) for components , using Pull list u can transfer stock from replnisment stoarge loc to prod storage loc.

    Please ensure the following settings at front screen ofpull list,

    Staging Type: "stor.loc.leve "tick mark

    Selection periods for req: Finish date of process order.

    Global settings:-> Dialog control->

    create Rep.propsal= Automatic

    Stage rep .propasal= Automatic,

    Along with standard seetings of pull list, if u do above settings, and access with process order number, system will give missing part overview and replnishment proposal for non stock components of process order.

    please try and comeback

    regards

    pradeep

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2007 at 10:28 AM

    Dear Amit,

    As you must be aware in material staging components for a header material(for which Process Order is created) are staged. In MF60, click on Production/Process Order tab .In selection remt. filed enter the finished date of your order.Execute.you will get the components list.Double click on the line item'Details tab'.You will get below the list of Production/Process Orders from which reqmt. for this component is generated.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.