hi ,
My question is that one machine to manufacture
1-3 nos take 30 min
4-6 takes 60 min
7-9 takes 90 min
...
i. e if a production order has to manufacture
1 no- 30 min
2 20 30 min
3 no 30 min
4 no 60 min
.
.
.
.
.
How to say this situation to the system as standard values in production order.
kindly help me
thanx in advance