Snapshot Versions - Notes - cProjects

Former Member
0 Kudos

Our user plans on using snapshot versions weekly to track changes to their project. They want to see the notes captured in the snapshots. We just realized that the notes are not being saved in the snapshots.

Is this a bug? Is there a way to have the notes captured in the snapshots?

Thank you,

Wendy

Message was edited by:

Wendy Miller

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Wendy,

This is not a bug. Notes and a few other stuff do not figure in the versions.

Thanks...

Answers (3)

Answers (3)

Former Member
0 Kudos

SAP created note 1117182 on 11/21/07 for this issue in a response to a message that we sent.

igor_prokofiev
Explorer
0 Kudos

Note 1117182 should solve this problem

Former Member
0 Kudos

Dear Miller

If u mean PS text as notes then SAP provides u a solution for the same to be copied to the project snapshot version. Please revert if my question is correct, to provide u with the solution.

Regards

Murali

Former Member
0 Kudos

Murali,

We are using cProjects. Is your message referring to Project Systems (PS)? I should have been more clear about this in my message.

Thank you,

Wendy

Former Member
0 Kudos

Dear Wendy

Yes i was referring to PS, i dont have any idea on c-projects.

Regards