Record Mp/Counter Reading for future time(1 day) via measurement document IK11

Oct 04, 2017 at 04:20 PM

54

avatar image

My client has a requirement of recording MP/counter reading for future time at least 1 day in advance via measurement document. At present if I am trying to record reading for future time I am getting the attached error as it comes with standard settings. I want to pass this check and allow system to accept readings for future time. Can anyone please suggest how to achieve this via some enhancement or some user exit.

mp-counter.jpg (75.1 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Peter Atkin Oct 24, 2017 at 03:10 PM
1

Have a look at the following IMG element: Define Measuring Point Categories


mp.jpg (43.3 kB)
Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Oct 05, 2017 at 11:21 AM
0

Hi Nimish

As per my knowledge not possible in IK01, just try with collective entry list.

Thanks

PM

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Abhishek

There is a configuration settings which de-activates the time zone and allow us to record readings for future timevia IK11 against the measuring point.

Need to know that. Please suggest me if you have any idea

0
Peter Atkin Oct 06, 2017 at 07:13 AM
0

Nimish,

This seems a strange requirement - why do you want to do this?

PeteA

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Pete my client has this requirement because due to some maintenance activities at plant the readings will automatically deviate from actual reading & that's acceptable. So for this purpose he want to record readings against measuring point via measurement document for at least 1 day in advance. I am using a Z tcode and uploading readings via excel sheet. I hope now you will understand the requirement.

Anyways I have found the solution, it can be done via standard configuration settings - we just have to define tolerance limits in seconds at Define measurement point categories path in SPRO

0
avatar image
Former Member Oct 09, 2017 at 07:22 AM
0

Hi Nimish,

A measurement document could be a reading or qualitative valuation of a technical object in real time. Recording a reading for future is not recommended so it's not available as a standard in SAP.

Please provide more detail about the requirement we can discuss for work around if any. Thanks

Regards

Varun M

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Pete my client has this requirement because due to some maintenance activities at plant the readings will automatically deviate from actual reading & that's acceptable. So for this purpose he want to record readings against measuring point via measurement document for at least 1 day in advance. I am using a Z tcode and uploading readings via excel sheet. I hope now you will understand the requirement.

Anyways I have found the solution, it can be done via standard configuration settings - we just have to define tolerance limits in seconds at Define measurement point categories path in SPRO