SAP PS - S_ALR_87013558 Report on Object Currency

shareeq_hussain
Active Participant
0 Kudos

Hi,

We need to generate the S_ALR_87013558 Report on Object Currency .

When we convert , budget is showing in Object currency but actual costs in Controlling area currency.

The report is not converting the actual costs from Conrolling area currency to Object Currency .

The available budget is not showing correctly. Help.

Regards,

Shareeq

Accepted Solutions (0)

Answers (2)

Answers (2)

iara_doliveira
Explorer
0 Kudos

Hello Shareeq Hussain,

Could you share if you came up with a solution for this topic?

I have the same problem.

Thank you.

shareeq_hussain
Active Participant
0 Kudos

Iara Oliviera,

No , we didnt get a solution.

Thanks

Shareeq

shareeq_hussain
Active Participant
0 Kudos

Did U get any solution. We still have this Availability Control Issue

kalpesh_agrawal
Participant
0 Kudos

hi,

Please change reporting currency in RPP0

Regards

Kalpesh Agrawal