PIR's Absence in MD04

Former Member
0 Kudos

Hi All,

There is situation in which I am unable to see my planned independent requirements for first three months of next year in MD04.

For the PIR's in question, we are using strategy group 90, with requirement type VSF and a custom requirement type (Sale from stock w/o inde.req reduction) for customer requirement type.

For PIR, the cusumption indicator is set to 1 which is consume only with customer requirements.

FYI,, there are no customer requirements (MD83).

Does anyone know what is going on and where should I look into to rectify this issue?

Your inputs will be greatly appreciated.

Thanks

Kole

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kole,

Check your Planning Horizon.

Regards

Krishna

Former Member
0 Kudos

I have checked the planning horizon and it there for 140 days..Planning horizon is not the issue.

ANyways I have answered this question by myself