Hi Friends,

I have done the Planning run ( Long term planning ) using tcode MS01. it has planned for the finished goods but the dependent requirements are not planned.

What can be the possible reasons???

Naren

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Narendra

Check u'r long term planning Procedure

1.) Create Planned Independent Requirememts (T.C MD61)

2.) Create Planning Scenario ( T.C MS31)

3.) Create Planning File Entries (T.C MS20)

Then Run Long Term Planning ( T.C MS01).Here Dependent requirements will not be created.Only Simulated requirements (SimReq) will be created.

You can view your stock requirements list through MS04

Reward points if usefull

Regards

Palaniappan

Message was edited by:

Palaniappan Sundaram

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi

pl. check material master for dependent materials .

Straetgy group in material master should be blank .

If it is not blank you have to make some more saettings.

Regards

YMREDDY

Former Member
0 Kudos

Mr.reddy,

I have checked the material master of dep materials and the strategy field is

blank. Please guide what to do??

Narendra

Former Member
0 Kudos

normally we use 40 for make-to-stock enviroment and 70 for configurable enviroment