HI,

Can anyone tell me in which table control record dates are there.When i put pay roll period it puts a date so from which table will it take.

Accepted Solutions (1)

Accepted Solutions (1)

sikindar_a
Active Contributor
0 Kudos

hai

i think u got the solution if ur query is solved pls close this thread and reward points for help ful answers

theja

Former Member
0 Kudos

Hi

Janhvi and I have already tried for T549 Q.,but our error is not getting corrected.For example when we put the period as 01 2007,and enter we get the dates as 01.03.2007.Similarly we are getting dates for retro accounting also.

Please solve the problem.

R.Saurabh

sikindar_a
Active Contributor
0 Kudos

hai

saurabh did u check the pay day rule while generateing pay roll

revert back if ur query is not answered

thanks

theja.C

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Janhavi,

As everybody already given answer, T549Q is correct answer.

May i ask still you need something?

If not close this thread.

Regards,

Manoj Shakya

Former Member
0 Kudos

Hi,

check table T549Q.

Regards,

Manoj.

sikindar_a
Active Contributor
0 Kudos

if u want get control period u have to generate pay roll period in order to do that u have to maintain period modifiers and date modifiers

table name :T549Q

thanks

theja

Message was edited by:

cherukuru theja

Former Member
0 Kudos

Hi,

Control Record period will come from Generate Payroll Period.