Has anyone configured a scenario where demand for an assembly item at the plant level comes from four sources:
- Customer demand (standard, driven by consensus demand at transferred to the plant via a sourcing relationship in the supply heuristic)
- Interplant demand, where the assembly has dependent demand propogated from another plant where the assembly is a component of a higher level parent
- In Plant dependent demand, where the assembly is used in manufacture of a higher level assembly in the same plant
- Independent demand
Hello Thomas,
The Input KFs are the one you need to focus. All the other Output KFs will have the demand propagated.
Please let me know if you have any further questions or doubts.
Best regards,
Matheus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Thomas,
We have that scenario in our company. We have Customer Demand, Independent Demand, Interplant Demand and Production Component(Demand from a BOM) configured to get our Total Demand. So if your Location Source for the assembly in the other plant is maintained you should be able to get the desired results.
Thanks,
Subash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thomas
It looks like technically you have only 3 types of demand - Dependent Customer Demand, Dependent Demand, and Independent Demand. Only thing is you have to make sure you have created and mapped correct Customer and location source along with the Production header/item data.
If my assumption is not correct, please provide sample in excel.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.