on 11-12-2007 6:15 PM
Hi All,
I need some help on these issues:
1. When transferring from SOP to demand management I face some issues like
Product group A has materials a, b, c
Product group B has materials a ,e, f
So when planning for Nov I require 20nos of a for Product group A and 50 nos of a for Product group B. I plan at header level and then disaggregate them.
When I transfer Product group A it transfers 20 nos of a
But when I trasfer Product group B it transfers 50 nos of a and replaces 20 to 50 instead of making it 20 + 50 = 70. Is there a way I can resolve it ?
Thanks,
Krish
Hi
After transfer to DM, it will be seen as plan for individual materials .
Please see in DM ( MD62) by selecting all active versions , if you have transfered into active versions.
If you have transfered into inactive versions, you select all versions.
There is no way to replace the qtys as you have updated.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Usually it is transferd in two different versions
In MC75/MC74
Enter different versions and make both active, so that total requirement will be considered in MRP.
One more option is to create a product group to get he total requirement of Material A after you disaggrigate group 1 and group 2, then you need to aggrigate the requirement of A to group3. Then transfer group3 after product group 1 and 2.
The second method we are using.
Message was edited by:
Rajesha Vittal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.