Hi experts,
I am trying to setup the automated planning run as follow :
Step 1: SAP001 (schedule sequence - sorting by start date) - Week 1 - 4
Step 2: ZSAP001 (schedule sequence - sorting by width) - Week 1
Step 3 : ZSAP001 (schedule sequence - sorting by width) - Week 2
The problem is that step 1 schedules orders that intercept with non-working times (between week 1 & 2 and week 2 & 3). These orders can't be rescheduled during step 2 and 3.
Message no. /SAPAPO/DM_SCHEDFAIL042 :
Is there a way to include these orders in one planning window (week 1 preferably) ?
OR
Can I prevent PPDS scheduling operations over non-working times ?
Any helpful hints please ? Thanks