Skip to Content

No requirement capacity or relevant to finite scheduling after confirmation

Oct 01, 2017 at 06:36 PM


avatar image

hi gurus,

Till production order release I can see capacity availability.but once after the confirmation there is an error no capacity requirement .

And also there is no requirement capacity in cm21.plz sug

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Oct 02, 2017 at 02:35 PM


Did you set up capacity reduction proportional to service in your work center? If you didn't, capacity requirements will be completely reduced upon confirmation.

Please read the following KBA to understand it in more details:

SAP Note: 1789680 - Capacity reduction proportional to service does not work as expected.