No requirement capacity or relevant to finite scheduling after confirmation

hi gurus,

Till production order release I can see capacity availability.but once after the confirmation there is an error no capacity requirement .

And also there is no requirement capacity in cm21.plz sug

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 02, 2017 at 02:35 PM

    Hello

    Did you set up capacity reduction proportional to service in your work center? If you didn't, capacity requirements will be completely reduced upon confirmation.

    Please read the following KBA to understand it in more details:

    SAP Note: 1789680 - Capacity reduction proportional to service does not work as expected.

    Regards,

    Caetano