No requirement capacity or relevant to finite scheduling after confirmation

Former Member
0 Kudos

hi gurus,

Till production order release I can see capacity availability.but once after the confirmation there is an error no capacity requirement .

And also there is no requirement capacity in cm21.plz sug

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Did you set up capacity reduction proportional to service in your work center? If you didn't, capacity requirements will be completely reduced upon confirmation.

Please read the following KBA to understand it in more details:

SAP Note: 1789680 - Capacity reduction proportional to service does not work as expected.

Regards,

Caetano