Hi Guys!
We are going live next month and, my client has mini master in his system. I configured om and pa and put in request. So since there is already config and master data in the Production, how do i go about it. if i transport the new config to prdn, and set up the employes master data according to the new config in the Prdn. Please advice...
Hi,
i depends on your requirement.
You could:
1. Delete mini master in Produktion
2. Make sure that your configration works also for the existing mini master
3. write a report which updates the mini master data to the new configuration
...
Hope this helps
Regards
Bernd