Hello PP Gurus,

I have a problem and hope that I will get the required solution for this:

1. We have a part say 'XYZ' which has a ”In house production time” of 35 days.

2. We have an a customer order request date 27/02/2008

3. MRP then suggests a planned order to meet the request date based upon the route time and not the ”In house production time” and this is where the problem lies, the route sheets shows a 2 week manufacturing time but in reality it takes 7 weeks to manufacture the part.

Note: We have 5 working days in a week.

So the question would be if we don’t want the planned order to reflect the route time how do we change this to automatically reflect the “In house Production Time” .

Thx in advance,

Rakesh

Message was edited by:

Rakesh Wade