I have the following scenario. FInish goods and semifinish are planned in apo.

When I create a planned order in APO the semifinish good is ok in the components. But when I save and transfer to ECC, it is creating the planned order duplicating the semifinish good. It is adding a position 9999 at the end of the components with the semifinish good. And then it is transfer back to APO with the semifinish good duplicated.

The semi has X0.

Accepted Solutions (1)

Accepted Solutions (1)

yasmin_alayyan
Advisor
Advisor

Hello Carlos,

Please check the note below:

2307727 - Duplicate component during creation of planned order

I think that it will solve the issue.

Regards,

Yasmin.

carlos_perez8
Participant
0 Kudos

Thanks so much

It solved my problem!!