Hello All
I am facing one problem in scheduling.
I have one production order 7734413.
Order is not released.
Always I am using back ward scheduling. I am working on 4.7 version
In production order Basic finish date is 07.11.2007 and basic start date is 28.10.2007.
In factory calendar Tuesday is holiday.
Now suppose I want to change finish date as 08.11.2007 and then I do scheduling.
Then system is proposing 09.11.2007 as finish date and start date as 31.10.2007.
That means after scheduling system is proposing one day ahead of finish date.
But if I enter finish date as any Wednesday then it is accepting the same as finish date.
Suppose I enter 14.11.2007 as finish date and if I do scheduling then system proposes 14.11.2007 as finish date. Here system is not proposing one day ahead of finish date.
Other details are as follows :
Schedule margin key
Opening period 10 days
Float after production 5 days
Float before production 2 days
Main thing I facing problem in scheduling on all days except on Wednesday.
Please let me know the solution.