Former Member
Nov 07, 2007 at 09:16 AM

Finish date changed in Scheduling

45 Views

Hello All

I am facing one problem in scheduling.

I have one production order 7734413.

Order is not released.

Always I am using back ward scheduling. I am working on 4.7 version

In production order Basic finish date is 07.11.2007 and basic start date is 28.10.2007.

In factory calendar Tuesday is holiday.

Now suppose I want to change finish date as 08.11.2007 and then I do scheduling.

Then system is proposing 09.11.2007 as finish date and start date as 31.10.2007.

That means after scheduling system is proposing one day ahead of finish date.

But if I enter finish date as any Wednesday then it is accepting the same as finish date.

Suppose I enter 14.11.2007 as finish date and if I do scheduling then system proposes 14.11.2007 as finish date. Here system is not proposing one day ahead of finish date.

Other details are as follows :

Schedule margin key

Opening period – 10 days

Float after production – 5 days

Float before production – 2 days

Main thing I facing problem in scheduling on all days except on Wednesday.

Please let me know the solution.