Process Order Operation Delay

Former Member
0 Kudos

Hii experts!!

In a process Order, an operation 0010 start at 1:00PM and end at 2:00 PM, operation 0020 start time is 2:00 PM, but if I want to start opeartion 20 instead of 2:00 PM, can i change or delay that opeartion.

I know in Production order we can provide Interoperation time, whereas same functionality is not given in Process Indutry, someone can plz tell me, whether we can change or Delay Operation timein Process Indutry.

If yes then how, do suggested me the procedure step by step.

Thanks in advance

Amit

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amit,

You can do this while creating/ changeing a Recipe.

You give these timings while maintaining "Relationship" between phases.

Regards

Krishna

Former Member
0 Kudos

Thank you ,

lemme check whether I can get satisfactory answer...

thanks once again

Former Member
0 Kudos

It looks like Krishna answer would only be option can be used ..

JK