The time stream for resource is not valid for the general display period.

Hi Apo Experts,

As I enter the product view in the PERIOD TAB, this error message pops up "Time stream from resource WC not valid for total display period".

Diagnosis was "The time stream for resource is not valid for the general display period. This can cause the display of the time buckets profile for this resource in the product planning table to be inaccurate."

Please, can someone help me understood what was this error mean and the cause? And maybe an idea on how to correct this.

Greatly appreciate your answer!

Thanks in advance,

Raymond

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Nov 07, 2007 at 03:56 AM

    Is this a PPDS or a SNP resource that you are talking about ? Can you check the time validity of the reosurce (days+ and - ). Can you let us know how that compares with Planning area initialization time period. the other thing is whether what you see is a warning or a error message.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.