In LE TRA Shiping type when I put " adopt all stages" then system is taking some extra leg why???

In LE TRA Shiping type when I put " adopt all stages" then while creating VT01N, in stages tab system is taking some extra leg why???

I am doing collective shipment in single mode of transfer

Means I created shipment from point A,B,C D then system is taking route as A to B, B to C and C to D, then A to C, A to D, D to A, etc.....

In route determination a have create route A to B, B to C and C to D.

1) shipment type I define " adopt all stages"

2)Determine leg "1Leg determine according to departure point & itinery.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 28, 2017 at 03:06 PM

    Hi,

    these settings

    "1) shipment type I define " adopt all stages"

    2)Determine leg "1Leg determine according to departure point & itinery."

    do NOT really fit together.

    The setting "adopt all stages" only does something when there is a route in your shipment document. This route is there either when you enter it in the document or when you copy it from the deliveries assigned to the shipment (and the stand only copies the route if it is the same in all deliveries). Check the header of your shipment document - is there a route?

    The setting "Leg determine according to departure point & itinerary" tries to use the sequence created by the sorting of the deliveries in the overview screen.

    And if you have both - well, I guess then you get things like you see on the screen.

    Brgds

    Juergen

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      ok, thankyou for replay

      means if i maintain " Determine leg: 1Leg determine according to departure point & itinery."

      then i have to maintan " Do not adopt stages wrt???