Impact of Material quantity in MRP

Sep 28, 2017 at 07:05 AM

36

avatar image
Former Member

Hi Team,

Could anyone explain how MRP Run will handle a material for which Material quantity Calculation is assigned.

Will MRP will determine required qty based on MQC or Not for the components.

Regards,

Dinesh Kumar

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

K V Kumar Sep 28, 2017 at 09:25 AM
0

Hi,

During MRP, system will not consider MQC. MQC will come in to picture only after the process order creation and during process order release normally.

Thanks

Kumar

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Oct 06, 2017 at 05:38 AM
0

Hello,

Greetings for the day.

If MQC run is not considered in MRP run, then we may face a qty shortage in process order execution know.

For e.g.,

"Material A" with BOM component as "Component B" of qty 2 nos.

MQC for "Material A" is defined in such a way that "Component B" of qty 10 nos (formula 2 nos * 5 = 10 nos).

As suggest, If MRP run is not considering MQC means, it will propose a MRP PR for 2 nos only. But shop-floor actually requires/consumes "Component B" of 10 nos to produce Material A.

How this GAP is filled by SAP ?

Regards,

Dinesh V.