Hi Team,

Could anyone explain how MRP Run will handle a material for which Material quantity Calculation is assigned.

Will MRP will determine required qty based on MQC or Not for the components.

Regards,

Dinesh Kumar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 28, 2017 at 09:25 AM

    Hi,

    During MRP, system will not consider MQC. MQC will come in to picture only after the process order creation and during process order release normally.

    Thanks

    Kumar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 06, 2017 at 05:38 AM

    Hello,

    Greetings for the day.

    If MQC run is not considered in MRP run, then we may face a qty shortage in process order execution know.

    For e.g.,

    "Material A" with BOM component as "Component B" of qty 2 nos.

    MQC for "Material A" is defined in such a way that "Component B" of qty 10 nos (formula 2 nos * 5 = 10 nos).

    As suggest, If MRP run is not considering MQC means, it will propose a MRP PR for 2 nos only. But shop-floor actually requires/consumes "Component B" of 10 nos to produce Material A.

    How this GAP is filled by SAP ?