Hi Team,

Could anyone explain how MRP Run will handle a material for which Material quantity Calculation is assigned.

Will MRP will determine required qty based on MQC or Not for the components.

Regards,

Dinesh Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

dineshcbe
Active Participant
0 Kudos

Hello,

Greetings for the day.

If MQC run is not considered in MRP run, then we may face a qty shortage in process order execution know.

For e.g.,

"Material A" with BOM component as "Component B" of qty 2 nos.

MQC for "Material A" is defined in such a way that "Component B" of qty 10 nos (formula 2 nos * 5 = 10 nos).

As suggest, If MRP run is not considering MQC means, it will propose a MRP PR for 2 nos only. But shop-floor actually requires/consumes "Component B" of 10 nos to produce Material A.

How this GAP is filled by SAP ?

Regards,

Dinesh V.

former_member184574
Active Contributor
0 Kudos

Hi,

During MRP, system will not consider MQC. MQC will come in to picture only after the process order creation and during process order release normally.

Thanks

Kumar