Stock at subcontractor

Dear Friends,

I have case like I have certain stock at subcontractor and now his code is changed. So how can transfer stock at his old vendor code to new vendor code.

Please guide.Thanks in advance.

Regards,

Amar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 06, 2007 at 08:51 AM

    Hi

    U need to bring back stock Reverse by MB1B 542 movement cancell PO

    and then raise new PO with new vendor code and pass MB1B with 541 Movement to post stock to new vendor code

    Vishal...

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Amar

      i think there is no direct way to trasfer stock from one vendor to another vendor as lot of legal requirements are there

      Vishal...

  • avatar image
    Former Member
    Nov 06, 2007 at 10:03 AM

    Hi,

    It is not possible to transfer subcontracting stock from one vendor to another. This movement type does not exist.

    You have to get the material back to your storage location, and send it again to the other vendor.

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      OK friends thanks a lot.

      I am keeping this note open and if anybod finds anything which is different than this then reply.

      Regards,

      Amar

  • avatar image
    Former Member
    Dec 02, 2007 at 05:39 AM

    thanks