Can we assign different company codes to different WBS Elements in one proj

Hi,

Can we assign different company codes to different WBS Elements in one project in SAP PS?Can you please this scanario in detail.

Thanks

Muzamil

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 02, 2007 at 03:27 AM

    Hi,

    Yes, different WBS can have different company codes. But the company codes must all be assigned to the same Controlling Area.

    However, when it comes to changing company codes at WBS level, please note that you cannot change the company code if plan/actual values, commitments, or budget exist.

    SAP documentation can be refrerred for further details.

    Reagrds

    muraleedharan.R

    091 9880028904

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Muraleedharan,

      Need advice regarding different company codes in one WBS. We have issue that in the basic data tab, we assigned to company code FNW. And in the assignment tab, it assigned to IGW company code. And now the project has been TECO, and it shows there are WIP to these two company codes, by right it should be only have WIP to FNW. In addition, when i check the settlement rule it also created two accounting document to FNW and IGW. How can i reverse one accounting document, since i could not change the company code in assignment tab because the status is already TECO.

      Really need your advice. My email is denis_evitanto@yahoo.com