I am on PPM1.0 on Hana 1610 on Premise version. PPM is installed on the same box as PS.

1. I have done the Financial Settings in Base System interface and linked the Value type 4 with Cost elements.

2. I have linked PS Project, WBS with PPM item in Object Link.

3. When I execute RPM_FICO_DATA_TRANSFER and it sucessfully transferred. no error or warning

4. I check table RPM_FIDATA and the data exists.

However, I dont see the Financial planning screen updated in PPM.

Can someone help, what went wrong?



10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Judith Gabriel
Oct 04, 2017 at 01:01 PM

Dear Anjali,

Start report /RPM/FICO_INT_PLANNING with the selection "planning, rollup" for the item. Then the datas should be transferred from table RPM_FIDATA to table /RPM/FIN_PLAN.