Hi All,
I am scheduling the standard realignment program parallally in my custom program. it is only completing the realignment process for some 13 records and rest 28 records are not getting realigned..... while seeing the jobs only 1 job gets completed and other failed..... following are the job logs :
1.
Job started
Step 001 started (program /SAPAPO/TS_REALIGN_COPY, variant &0000000000037, user ID XYZ
SQL: 01.11.2007 09:08:47 MQHCDB
ALTER TABLE "/BIC/FZDP_POS1" MONITORIN
SQL-END: 01.11.2007 09:08:47 00:00:00
ABAP/4 processor: MESSAGE_TYPE_X
Job cancelled
2.
Job started
Step 001 started (program /SAPAPO/TS_REALIGN_COPY, variant &0000000000042, user ID XYZ)
SQL: 01.11.2007 09:08:48 XYZ
ALTER TABLE "/BIC/FZDP_POS1" MONITORIN
SQL-END: 01.11.2007 09:08:48 00:00:00
No liveCache anchor found
Job cancelled after system exception ERROR_MESSAGE
Can you please figure out what can be the problem for the same....
Please let me know if some more details are required !!!