on 10-31-2007 7:25 PM
Hi,
Did anyone had this issuse before, I entered 4 hrs to an attdence type in CATS and approved and saved the record using CATS_APPR_LITE. Now I am going back to time sheet and making the 4 hours as 0 hrs and saving it. now if i pull up the record through CATS_APPR_LITE to approve the change, it is still showing 4 hrs and approved.
It seems that CATS is not processing "Changed after approval" status correctly. Do any one know where the issue lies in?? Is it an authorization issue or Basis or Development????
We are on SAP ECC 6.0.
Thanks in advance.
Did you release that entry after you approve and change. Please release the changed entry, then it will show up in CATS_APPR_LITE as 0 hrs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok, the basic thing is when u change data in CATS u need to release it before/after saving.
And if thats not the case type in 10 to 60 for the Processing status field in CATS_APPR_LITE report.
Status Indicator
In process 10
Released for approval 20
Approved 30
Approval rejected 40
Changed after approval 50
Cancelled 60
and now u should be able to see all the changed records with the respective statuses..........
reward points if helpful
cheers
SA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You will have a approved & a cancelled entry. And another entry for approval.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.