Dear CO friends,
The Costing view of the material master record, has 3 sets of fields for the Planned Price and Date from.
There is no Date To field.
The actual scenario is that the Planned price 1 is valid for a specific period of time. At the end of this period I need the Planned price to be deactivated (equal to zero).
The system prohibes the entry of Planned price = 0.
Planned Price Date From Date To (does not exist)
120 01/02/07 31/03/07
0 01/04/07 31/12/9999 Price 0 Not allowed
Are there any ideas how to implement the above?
Thanks in advance for yr time.
Regards,
Elly