Variance calculation

Former Member
0 Kudos

Hi All,

When execute variance calcultion the system does not calculate the input price variances?

Regards

Riki

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Riki,

The system can only calculate input price variances if quantities were specified in addition to the planned and actual costs. The following conditions must be met for this:

Turn on the Material origin indicator in the costing view of the master record of all materials that have a large influence on your costs.

Uniform units of measure must be assigned to all input materials. That is, material costs can only be totaled under a cost element when such costs are carried under the same unit of measure.

If you want to calculate variances by cost element/origin group, you must already have entered an origin group in the costing view of the material master record for all material components.

If there is any problem please let me know

Regards

Raju.k,

Former Member
0 Kudos

Hi,

Well answer Mr.Raju.k

I resolved issue.

I ll assign full points

Riki

Answers (2)

Answers (2)

former_member188826
Active Contributor
0 Kudos

OKVG , Check if input price category is enabled for the variance variant you use.

Former Member
0 Kudos

Hi Sridhar,

That is already checked thanks for response

Riki

former_member188826
Active Contributor
0 Kudos

Which release are you in?

Former Member
0 Kudos

When you execute the variace calucation, the system only calculates the difference between planned and actual costs incurred.

Assign points if helpful

Former Member
0 Kudos

Hi PV,

Thanks for early response please try understand my problem.

But your answer is not related to problem.

Could please suggest me how to resolve below issue.

System does not calculate the input price variances?

Regards

Riki

Former Member
0 Kudos

Hi ,

can you give an instance as example...

cheers

Pk