Hi All,

I have a scenarion file to RFC. The scenario works great, except if i have multiple files. The system locks up the material code.

Is there a way to force XI to process the files 1 after the other 1 has been processed?

Kind Regards,

Danny

Accepted Solutions (0)

Answers (2)

Answers (2)

nisarkhan_n
Active Contributor
0 Kudos

Use the EOIO QOS int he file adapter, this makes sures the files aer being processed in the order win which they enter queue...for this you have to maintain the queuename.

Chk this link -> Quality of Service EOIO section , it answers ur question.

http://help.sap.com/saphelp_nw04/helpdata/en/7b/94553b4d53273de10000000a114084/content.htm

former_member181959
Contributor
0 Kudos

Hi.

May be commit work can help you in this.

You need to execute the commi work after every transaction.

Hope this helps.