Former Member
Oct 29, 2007 at 07:17 PM

R/3 Converted Planned Order to APO Changes dates

17 Views

Hi,

We have several users who create planned orders in R/3 and then they convert it to production orders using conversion. This orders come to APO and sit in Produciton confirmed key figure in SNP Planning Book as category "AD".

The problem is that this orders are on the resource with 40 hours a week and 8 capacities. They take 3 week to manufacture for example in R/3 and that calculations are correct but when it comes to APO, it show start date of 4 months earlier than what R/3 is showing. 4 months is not exact number. It keeps changing. We are not able to figure out why APO and R/3 differs in Order Start Date ?.

Can you help ?.

Thanks.